24 May 2013

Presidential concerns about the State Budget

At the end of February, President of the Republic Taur Matan Ruak promulgated the RDTL General State Budget for 2013. At the same time, the President wrote a letter and memorandum to Members of Parliament, expressing his concerns, including about budget execution rates, expensive speculative projects, inflation, low allocation for human development, the Tasi Mane project and unemployment. Many of his suggestions address the same issues as La'o Hamutuk's submission to Parliament.

Although the President's office did not make his letter public, La'o Hamutuk obtained it from Parliament and is making it available in Portuguese and our unofficial English translation, which follows (links and graphics added by La'o Hamutuk).

President of the Republic
GENERAL STATE BUDGET (GSB) FOR 2013
General Notes and Recommendations

1. The President notes that the rate of execution of the State Budget for 2012 will have been about 70%, and this corresponds to spending of approximately USD $1,200 million. In the GSB for 2013, the Ad-hoc Committee submitted an alternative proposal (to the initial proposal of $1,797.5 million) of $1,647 million. This proposal was approved with 64 votes in favor and 1 abstention.

2. Of the total value of the Infrastructure Fund planned for 2012, only 49% of the funds were spent. If you exclude the funds for the electrification project of the country, the rate of execution of the Infrastructure Fund in 2012 was significantly lower: 29%.

3. The total expenditures of the 2013 State Budget are $1,647.519 million, which was reduced by $155 million (-8.3%) from the Government’s initial proposal. This reduction is mainly achieved through reduced expenditure on Development Capital / Infrastructure (-$135 million) and a decrease of $20 million in spending on goods and services. The reduction in goods and services is due to the fact that this budget will be approved 2 months later than what the law determines (1 January 2013).

4. “The $1,501.219 million fiscal deficit of the state budget”, “is financed with $787 million from the Petroleum Fund, $43.6 million through the use of public credit” (soft loans from international donors), “$409.8 million in the balance carried forward from Special Funds” (mainly the Infrastructure Fund), and “$260.8 million from the balance in the Treasury Account.”

5. The President welcomes the reduction in the amount of the state budget compared with last year. However, taking into account the history of low rates of execution,  the President draws attention to the urgent need to complete the execution of this budget. There appears to have been a high tone of optimism in the definition of expenses to carry out, especially for projects that end up not being executed.

6. The President notes that the relative abundance of financial resources has given rise to speculative projects with inflated prices with significantly prejudice to the public interest.

7. The President welcomes the statements made by Members of Parliament as well as the affirmation of the Prime Minister, with respect to the functions of supervision and monitoring of project execution through quarterly meetings to take place between the Parliamentary Standing Committees and the respective members of the Government. The President believes that these actions will better protect the national interest.

8. Average annual rates of inflation reached 13.5% in 2011 and 11.8% in 2012. The President hopes that this GSB can contribute to reducing  inflation that the country has suffered during the last two years. These values greatly reduce the purchasing power of civil servants, mainly those who earn lower wages, and especially citizens with low incomes.

9. The President notes that, on the one hand, in the structure of expenditure in this State Budget, 46% is allocated to the construction of infrastructure, prioritizing spending on electrification of the country, road reconstruction and the Tasi Mane project. On the other hand, there is much less spending in key areas of human development -- education receives only 5.6%, health receives 3.7% -- and agriculture, which involves about 80% of the population, gets only 1.5% of the total budget.

10. The President welcomes the special allocation for Oecusse. However, he regrets the lack of a budget for the “planning” of Dili, the capital of the Republic which welcomes the diplomatic community and is the main gateway to the Country.

11. Regarding the Tasi Mane project on the South Coast, the President understands the reasons that appear to justify not having changed the intended amount. However, he would like to see a public explanation of the reasons for allocating these funds, in particular when compared with other expenses with obvious social utility. For example, two kilometers of highway are likely to cost $20 million and the budget allocated to agriculture is about $25 million.

12. The President was informed that losses caused by illegal fishing amount to more than $200 million per year. The President regrets not finding an adequate response to this problem in this budget, which continues to affect the potential for national fishing.

13. With regard to domestic revenues, the President hopes that the efforts of the Executive for better tax administration and collection of taxes, duties and other revenues will be effective. The President intends to urge firm measures to combat tax evasion and capital flight, which will allow for greater prudence in using money from the Petroleum Fund.

14. Responding to unemployment is an unavoidable necessity. The President hopes that this GSB can generate more permanent jobs, contributing to a significant reduction in poverty that affects more than 50% of households in the interior of our Country. The President also hopes that this budget will contribute to a tangible decrease in the asymmetry between the capital Dili and other districts.

17 May 2013

LH asks Australia to respect Timor-Leste's sovereignty

The Australian Parliament recently published 72 submissions to its Inquiry on Australia's relationship with Timor-Leste to the website of the Subcommittee on Foreign Affairs.  La'o Hamutuk was the only Timor-Leste organization to write to the Committee, and we raised the following points.
  • Our relationship should be based on mutual respect for sovereign and human rights.
  • Timor-Leste’s proximity to Australia is an opportunity, not a risk.
  • We appreciate Australian support since 1999, but history still haunts our peoples, as does Australia’s continued theft of Timor-Leste’s oil and gas resources.
  • Australia’s generous assistance can meet our people’s needs more effectively by prioritizing human security and reducing unnecessary overhead.
  • Timor-Leste and Australia should settle our maritime boundary based on current international law and good-faith arbitration or negotiation, including use of legal processes.
  • Australian military forces should be more forthcoming and accountable when their activities here injured or killed Timor-Leste citizens.
  • Ties between our peoples provide good examples for better links between our states.
The text of our submission follows, or download a PDF here. We also wrote a background sheet and updated information about our unresolved maritime boundary.

Celebrate La'o Hamutuk's 13th anniversary!

Please join us to celebrate thirteen years of Walking Together with La'o Hamutuk. Although both the nation and the organization have come a long way since 2000, the journey continues.  We invite our friends and colleagues to celebrate our anniversary on
Friday, 24 May 2013
3:00-6:00 pm
La'o Hamutuk's office, Bebora, Dili

Ho laran ksolok ami konvida belun sira hodi mai hamutuk ho ami atu selebra aniversario La'o Hamutuk ba dala 13 iha:
Sesta, 24 Maiu 2013
Oras 15.00-18.00 OTL
Edifisiu La'o Hamutuk, Bebora Dili


01 May 2013

Suai Supply Base: benefit or boondoggle?

The centerpiece of Timor-Leste’s Strategic Development Plan is the Tasi Mane Project (TMP), a corridor of petroleum infrastructure along the southwest coast of this country which includes a supply base in Suai (Covalima district), refinery in Betano (Manufahi district), LNG plant in Beaçu (Viqueque district) and a highway to connect them.

This article summarizes La’o Hamutuk’s extensive new web page on the Suai Supply Base (SSB), the first component of TMP. That page has more information, documents, analyses, presentations, maps and graphics, and will be updated regularly.
English: http://www.laohamutuk.org/Oil/TasiMane/13SSBen.htm
Tetum: http://www.laohamutuk.org/Oil/TasiMane/13SSBte.htm

The main project in Suai will be a port (breakwater and jetties), storage yard, warehouses, offices, fuel tank farm, helipad and future industrial park in Kamanasa Suco, Covalima District. Its 1,113 hectares are almost entirely agriculture land, a sacred area for local inhabitants.

In addition to the Supply Base itself, the Covalima components of the Tasi Mane project will include an expansion of Suai airport, a 208-hectare “Nova Suai” new town to house workers from the project, and a divided highway that will eventually go 150 km to Beaçu.

The project originally included a seaport in Suai Loro, which was cancelled because it would have been redundant with the port in the Kamanasa Supply Base, which can also serve as a cargo terminal.

The Supply Base will be built, owned and operated by Timor-Leste’s state-owned oil company TimorGAP and their subcontractors, with estimated operating costs of $8 million per year.

Supply Base construction will be phased over many years, but TimorGAP plans to fence in the entire area in Kamanasa and exclude local use, perhaps as soon as the end 2013.

The rest of this blog posting discusses key issues about the Suai Supply Base, including
  • History and current status
  • Project cost -- which has multiplied by 14 in less than three years
  • Environmental Impact Assessment, including documents and information gaps
  • Rough estimate showing that the SSB may not recover its investment
  • Suai community views and the recent land transfer